Skyscraper Data Centers at Nuclear Plants: Run Them as House Load?
Happy says nuclear plant sites should host tall data centers fed straight from the generator. What house load really is, what FERC did at Susquehanna, and what changed after.
Happy has a simple pitch. Build tall data centers right on nuclear power plant sites and feed them straight from the plant, the way the plant feeds its own pumps and controls. No long power line, no grid congestion charge, and the rack space sits behind one of the best guarded fences in the country. He worked at Oyster Creek and interned at Fermi 2, so he knows what is inside that fence.
House load, and why a data center is not it
Every power plant uses some of its own electricity. Pumps, fans, cooling systems and control rooms all run whether or not the plant is selling power. That is house load, also called station service. It is part of how the plant runs, and at a nuclear plant much of it is tied to safety.
A data center on the same site is different. Regulators call it co-located load: an outside customer wired to the plant's side of the connection instead of to the grid. In the Susquehanna case the grid operator, PJM Interconnection, put it plainly: co-located load is not network load.[1] That label decides who pays for what.
The real test case: Susquehanna
The Susquehanna Steam Electric Station in Pennsylvania has two 1,260 MW units, 2,520 MW in all.[1] In March 2024 its owner, Talen Energy, sold its 960 MW data center campus next door to Amazon Web Services.[3] The plant was already allowed to serve 300 MW of co-located load. PJM asked to raise that to 480 MW.[1]
On November 1, 2024 the Federal Energy Regulatory Commission said no, 2 to 1. The majority said PJM had not shown why this one plant needed special terms.[1][3] Chairman Willie Phillips dissented and called the decision a step backward for reliability and national security.[2] Talen asked FERC to reconsider and said it would take the case to a federal appeals court.[7] The utilities that protested argued the data center would dodge its share of the grid, a cost shift they estimated at up to $140 million a year.[1]
What changed after
In June 2025 Talen and Amazon rebuilt the deal: 1,920 MW of Susquehanna power through 2042, delivered in front of the meter, meaning through the grid like any big customer. That version needed no FERC approval, and Talen expects about $18 billion in revenue from it.[4][6] In December 2025 FERC found PJM's rules unjust and unreasonable and ordered it to offer new transmission service choices for co-located load.[5] So the door is open again, but with a grid bill attached.
The other path is buying the whole plant's output. Constellation Energy plans to restart Three Mile Island Unit 1, shut in 2019, as the Crane Clean Energy Center, about 835 MW, under a 20 year deal with Microsoft.[9] Constellation says the plant itself can be ready in 2027, but PJM will not finish the transmission upgrades it needs to connect until 2031.[8] That is the strongest argument for Happy's version: a data center fed on site would not have to wait four years for new power lines.
So is Happy right?
On the engineering, mostly yes. The generator, switchyard, security and staff are already there, and a data center next to the plant skips the long line. The catch is the label. A data center is not house load, and when it leans on the grid as backup during outages, other customers want it to pay. Regulators have spent two years on that question. A tower full of servers inside the fence would also have to clear nuclear safety and security rules that nobody has tested yet.
Sources
- FERC, Order Rejecting Amended Interconnection Service Agreement, PJM Interconnection, Docket ER24-2172, Nov 1, 2024 (Susquehanna 2,520 MW, two 1,260 MW units; co-located load 300 MW to 480 MW; "Co-Located Load is not Network Load"; protesters' estimate of a cost shift up to $140 million per year)
- FERC, Chairman Willie Phillips dissent, Docket ER24-2172, Nov 1, 2024
- World Nuclear News, "Regulator rejects amended Susquehanna power agreement," Nov 4, 2024 (2 to 1 vote; Talen sold its 960 MW Cumulus data center campus to AWS in March 2024)
- The Register, "Amazon has changed its nuclear deal in Pennsylvania to bypass grumpy regulators," June 12, 2025 (1,920 MW through 2042, front of the meter)
- FERC, "FERC Directs Nation's Largest Grid Operator to Create New Rules," Docket EL25-49, Dec 2025 (PJM tariff found unjust and unreasonable; transmission service options for co-located load)
- Utility Dive, "Talen to sell Amazon 1.9 GW from Susquehanna nuclear plant," June 11, 2025 (1,920 MW through 2042, front of the meter, no FERC approval needed; Talen expects about $18 billion in revenue over the contract)
- American Public Power Association, "Company to Pursue Appeals Court Option in Wake of FERC Order on Data Center and Nuclear Plant," Dec 31, 2024 (Talen rehearing request Nov 20, 2024; intent to appeal)
- World Energy, "Constellation exec says Three Mile Island can't connect until 2031," Mar 27, 2026 (plant ready in 2027; PJM transmission upgrades not done until 2031)
- Constellation Energy via Business Wire, Crane Clean Energy Center restart and 20 year Microsoft power purchase agreement, Sept 20, 2024 (about 835 MW; Unit 1 retired 2019; expected online 2028)
Inspired by Happy. Prepared by an unnamed model (no MODEL line returned). Reviewed and edited by Claude.
Revision history (R0 current)
| Rev | Date | What changed | Page |
|---|---|---|---|
| D1 | Nov 22, 2026, 1:52:30 PM CST (saved on arrival; chat message 1:52 PM, minute only) | What the model returned, unedited. No MODEL line, no sources, markdown with dashes. Prompt handed out Nov 22, 1:47:30 PM CST. | view |
| R0 | Nov 22, 2026, 1:58:08 PM CST (reviewed and posted) | First publish. Rewritten to house style by Claude (Opus), every claim checked and cited against FERC, Constellation, World Nuclear News and The Register; 2025 developments added. | view |